Manager app
Escalations
4
Critical
2
Phone camera
automatic
Scanner website
automatic
Frames to backend
automatic
Primitive Recognition
automatic
Plan comparison
automatic
Error list
with feedback
Live dashboard + worker app
with feedback
Reorder material
CriticalDecision openNorth storage and strip foundation C
Steel and concrete are below expected stock.
Worker app confirms 4/6 steel pallets and 28/38 t concrete.
Steel shortfall
2 pallets
Concrete shortfall
10 t
Cost risk
18,400 EUR
Impact: Concrete section B3 can only run partially today.
Owner: Procurement + site management
Due: today 13:30
Trigger an express reorder for 2 pallets B500B and 10 t C30/37.
Wrong door leaf installed
CriticalCheck removalLevel 1, east corridor, axis B3
Detected door leaf does not match the plan position.
Recognition classifies T90-RS instead of T30-L; worker should confirm.
Confidence
79%
Trade
Interior
Removal
likely
Impact: Fire-safety acceptance and interior sequence are blocked.
Owner: Interior site management
Due: today 15:00
Clarify plan version, check delivery note, and stop the installation crew.
Construction is slower than planned
WarningSchedule riskSection B3 and south facade
Several primitives block the same workflow path.
Material is missing, the window element is incomplete, and the plan change is not implemented.
Schedule impact
+2.5 d
Affected trades
3
Open worker checks
5
Impact: Forecast: 2.5 days delay if the reorder is not confirmed today.
Owner: Overall site coordination
Due: today 16:00
Retakt the concrete sequence, prioritize interior work B3, and plan window sealing separately.
Plan revision R7 not on site
WarningAsk planningLevel 1, east corridor
An old door version appears on site.
Scanner detects T-04/T90-RS; expected is T-05/T30-L after revision R7.
Planrevision
R7
Conflicts
2
Cost risk
6,200 EUR
Impact: Wrong ordering or installation can trigger costs and removal work.
Owner: Planning + site management
Due: today 14:15
Push revision R7 to the crew and check procurement against the current door list.
Material is missing, one part is wrong, and the plan revision has not arrived on site.
Confirm reorder today and stop door/window installation until plan approval.